APP Open Season Details

I've had some time to scan through the "APP" (Alaska Pipeline Project) open season documents and here are a few first impressions:

  • In Service Date: 2020 - Hey I'll be SIXTY! OMG I'll be SIXTY!
  • Cost to move gas to Alberta: $2.43-$3.13/MMBTU
  • Cost to move gas to Valdez: $2.22-$2.89/MMBTU
  • Point Thomson is a vital part of the overall project
Overall I'm encouraged by the numbers - it actually looks achievable. At a minimum the cards are on the table and other parties can start ciphering on the cost of an LNG plant, the value of Alaska Gas for tar sand production, and a reasonable tax structure.

Anybody want to take a stab at the cost of the LNG plant? My quick calculation say the LNG plant would have a capacity of 18 million tons per year LNG and cost $31 Billion. Somebody check my math. We really need a good cost estimate of the LNG plant to compare the options.

Here's some images from the document showing the pipeline options and capacities:





Assorted headlines:

EDMONTON JOURNAL:Alaska gas could bypass Alberta Option would send fuel to Valdez

UPI TransCanada details Alaskan pipeline plan

GLOBE AND MAIL: TransCanada seeks Alaska project commitments

OIL & GAS JOURNAL: Alaska Pipeline Project files open season plan

REUTERS: Exxon, TransCanada raise Alaska pipeline estimates

Monday, January 11, 2010

Judge rules for Point Thomson

Department of Natural Resource Commissioner "Playa Hater" Tom Irwin was handed a defeat in court Monday for failing to give due process to the Point Thomson Unit (AKA ExxonMobil and others).