Project Pulse: Flatlined


The latest Alaska Pipeline Project's Pre-Filing Status Report for 2ed Quarter 2013 is a one pager that shows less progress than the last no-progress report (LINK TO FERC ELibrary).

Here's the content of the report:
  • Open Season:  Notice was provided to the Commission on May 3, 2012 that the first binding Open Season was terminated as of that date. 
  • Public Outreach: A Stakeholder Engagement Plan was filed with the FERC on April 5, 2010. No engagement has occurred in the past quarter. 
  • Pipeline Right-of-Way and Engineering: Pipeline engineering and technology development work initiated to date has been completed and documented.
  • Gas Treatment Plant (GTP): Engineering deliverables have been archived for potential future use.
  • Environmental Planning and Permitting: No Environmental planning or permitting work has been conducted in the past quarter, although invoices for 2012 work continue to be processed.
  • Project Meetings: The project had no additional contact with federal, state, and local agencies that have regulatory approval or other interests regarding the Project in 2Q2013. 
  • Project Activity in Canada:FERC requested an update of Project activities in Canada in these activity reports. Completed remaining field program work and permit requirements with federal and territorial and provincial governments.
Aside from Bill Walker no one seems to be agitated by this de facto termination of the project. According to some observers it's not time to blow down the North Slope gas. (LINK).  If it's not time to blow down the gas why does Alaska continue to burn AGIA money?

Here's a look at the AGIA funds expended as of the January 2013 report:

 

If the Quarterly FERC report is an accurate indication of the project health why do Alaskans continue to shovel money at it?